Our Projects
Project Da Vinci
2018
For this project, 6 Optic systems were installed on Luffing cranes.
The use of the optic systems improved the work efficiency of the crane and in turn decreased the time cycle of lifting and lowering by an average of 30%.
The result: A cost reduction estimated in hundreds of thousands of Shekels (NIS Israeli currency).
The conclusion: Our crane operator optic system, provides a solid return on investment from the very first day of installation.
In addition, the system drastically improves the safety environment on site and especially on sites packed with multiple contruction cranes.
The Artists Residence Project
2018
For this project, 6 ELC systems were installed on Liebherr tower cranes.
This construction site was slightly more complex due to the fact that the compound had 13 ELC systems of other consctruction companies who were building in the compound.
This was another technological challenge due to the amount of different cranes working on site.
Coding of all systems was required in order to avoid disturbance between the systems and enable smooth and seamless reception signal.
This allowed the crane operators to work with great speed and efficiency while maintaining utmost levels of safety.
The systems also made it possible for the crane operators to work during night time effortlessly and with no issues.
On this construction site we installed a 360 degree view module on one of the cranes for a full surrounding area view.
Project White Beach
2017
For this project, 4 ELC systems were installed on Liebherr tower cranes.
On this construction site, four prestigious residential buildings were built, each standing at 140 meters tall and adjacent to the shoreline.
The durability of our ELC systems allowed continuous, uninterrupted work for 2.5 years.
Our systems have increased crane efficiency thus saving the contractor - Ashtrom hundreds of thousands of Shekels (NIS Israeli currency).
Project Yossef Burg
2020
For this project, 3 ELC systems were installed on Liebherr tower cranes.
In this compound, three residential building clusters were built, using our ELC systems allowed the contractor to complete the project with great efficiency and ease.
Our ELC systems allow the crane operators to work in maximum efficiency while maintaining utmost safety.
Project Or Yam
2019
For this project, 6 ZOOMLION tower cranes were erected.
On these cranes we installed our crane operator optic ELC systems, on this construction site there were 15 cranes in total with varying ELTA optic systems installed on them.
The challenge here was to code the systems broadcast feed to prevent image leakage and disturbance between the cranes around the site.
The systems here allowed the crane operators to provide efficient and quick service to the construction crew and the contractor.
The systems also made it possible for the crane operators to work during night time effortlessly.
Project Ganey Tikva
2017
For this project an ELC system was installed on a Potain tower crane.
The system allowed the crane operator to work with maximum efficiency and for the contractor to deliver the building project expeditiously.